This page may take a little while to load, there's 250,000 bytes of thumbnails
on it.
Click on any thumbnail to see a larger image.
December 26, The Beginning
Woodbury Construction were
engaged to construct our house.
-Here's
the house site after the initial clearing. Notice how the two oak
trees frame North Pack Monadnock Mountain.
March 14
-After
blasting for a cellar hole.
+
-A
nearby waterfall, just beyond the western property boundary.
May 15-21, Sawyering
+
-Wolf
Custom Cutting brought their equipment to our site.
-They
made some skids.
+
+
-Several
Beams.
+
+
+
-Some
curved braces.
-And
lumber as a by-product.
May 29, Footings
+
June 3, North Pack Monadnock
-The
Summit
+
-The
View
June 4, Basement Walls
-Mike
supervised the pouring of the basement walls by Carroll
Concrete.
-Setting
up.
-Dry,
notice all the nubs--they have to be pounded off by hand.
June 6, Weather
+
-Cool
cloud effects.
June 8, Foundation Work
-The
foundation gets water-proofed.
-The
foundation gets insulated.
June 10, North Pack Monadnock
Part 2
-From
North Pack looking North
-From
North Pack looking North with Labels
-From
North Pack looking North.
-The
Clearing,
-Magnified
June 10-13
-Crushed
rock was placed in the cellar and pounded down.
-Lines
were run to the well.
-Dirt
was back-filled against the foundation walls
-See.
-And
pounded down.
June 14, Durisol
-The
Durisol®
arrived.
June 17, Waste Mis-Management
-The
dumpster almost arrived.
June 18, Septic Tank
-The
Septic tank was installed.
June 18-24, The First Floor
Deck
+
+
+
+
+
+
+
+
-Alternate
view.
June 24, The Well
-This
rig drilled the well. McKenna Well Drilling Inc., (603) 563-8313,
Dublin, NH 03444
-This
was the view from the rig.
June 26-July 1, Durisol
Deployed
+
+
+
+
July 2, Basement Floor Poured
+
+
+
-More
Durisol progress.
July 11, Upper Deck
-The
future home of "The Boys".
-West
Side Story
July 14, Beta Test
+
-The
heartier members of the family camp out.
+
+
-Quarter
Moon in a Ten-Cent town.
-Sunrise.
July 11-August 15, Masonry Heater
+
+
+
+
+
July 15, Durisol meets Concrete
+
-With
appologies to "Wayne's World".
-Phil
fills.
July 22-24, And now the
heavy lifting
-This
crane from American Steel made all
the difference.
+
-Assembling
Bent 4 (Southernmost).
-Assembling
Bent 1 (Northernmost).
-
Assembling Bent 3.
-Bents
1&2 in place.
-Bent
3 added.
-All
4 bents (very large picture).
-Facing
South.
+
-Side
Views
-Need
a good contractor?
-Nice
detail.
-Icing
on the cake.
-Steve
Amstutz and the team from Amstutz Woodworking.
July 25-August 6, The Roof
+
-The
ridgepole is placed.
+
-Another
day's progress.
-
+
+
-The
view East from the ridgepole
August 5-15, Leaching Field
+
+
August 15, The Porch
August 27, Shingling Begins
-The
shingles were staged for easy deployment.
-Six
inches of copper flashing was added at the drip edge. Then Bituthene®
was applied to the roof to within one inch of the drip edge.
-Four
courses of EcoStartm rubber
slate shingles have been installed. The first course was upside-down
(on purpose).
-Looking
up from under the eves.
August 28, Shingling Continues
-Several
more courses have been aded.
-Up
close look
August 30, Shingling Continues
-Nearly
done on the west side.
-Several
braces have been removed.
September 3-4, The Porch
Roof
-Sheets
of copper are laid on the porch roof.
-finished
result.
September 10, Solar
-We
built the frame and attached the solar panels.
-Kind
of biospherical, huh?
September 10, All in review
of course
-Here's
the East side from the Northeast.
-Here's
the East side from the Southeast.
September 30, Santa-proofing
-The
Chimney and ridgecaps are installed.
October 8, Roughing
-Electric
wires have been roughed in and insulation has been blown into the ceiling.
-This
will supply the washing machine.
October 9, It's Alive!
-This
light is powered by the solar panels!
October 18, Macrohard Windows®
-South
-East
October 21, Plaster
-BlueBoard
has been installed on all walls and the ceiling.
+
-Then
it gets plastered.
-Foliage
October 23, Nature
-Nature
says, "Get moving!"