December 26, The Beginning
Woodbury Construction were
engaged to construct our house.
-Here's the house site after the initial clearing.
Notice how the two oak trees frame North Pack Monadnock Mountain.
March 14
-After
blasting for a cellar hole.
+
-A nearby waterfall, just beyond the western
property boundary.
May 15-21, Sawyering
+
-Wolf Custom Cutting brought their equipment
to our site.
-They made some skids.
+
+
-Several
Beams.
+
+
+
-Some curved
braces.
-And lumber as a by-product.
May 29, Footings
+
June 3, North Pack Monadnock
-The
Summit
+
-The
View
June 4, Basement Walls
-Mike supervised the pouring of the basement walls by Carroll Concrete.
-Setting
up.
-Dry, notice all the nubs--they have to be pounded off by
hand.
June 6, Weather
+
-Cool
cloud effects.
June 8, Foundation Work
-The
foundation gets water-proofed.
-The foundation
gets insulated.
June 10, North Pack Monadnock
Part 2
-From North Pack looking North
-From North Pack looking North with Labels
-From North Pack looking North.
-The Clearing,
-Magnified
June 10-13
-Crushed rock was placed in the cellar and
pounded down.
-Lines were run to the well.
-Dirt was
back-filled against the foundation walls
-See.
-And
pounded down.
June 14, Durisol
-TheDurisol®
arrived.
June 17, Waste Mis-Management
-The dumpster almost arrived.
June 18, Septic Tank
-The Septic tank was installed.
June 18-24, The First Floor
Deck
+
+
+
+
+
+
+
+
-Alternate view.
June 24, The Well
-This rig drilled the well. McKenna Well Drilling
Inc., (603) 563-8313, Dublin, NH 03444
-This was the view from the rig.
June 26-July 1, Durisol Deployed
+
+
+
+
July 2, Basement Floor Poured
+
+
+
-More Durisol
progress.
July 11, Upper Deck
-The future
home of "The Boys".
-West Side Story
July 14, Beta Test
+
-The heartier members of the family camp out.
+
+
-Quarter Moon
in a Ten-Cent town.
-Sunrise.
July 11-August 15, Masonry Heater
+
+
+
+
+
July 15, Durisol meets Concrete
+
-With appologies
to "Wayne's World".
-Phil
fills.
July 22-24, And now the heavy
lifting
-This crane from American Steel made all the difference.
+
-Assembling
Bent 4 (Southernmost).
-Assembling Bent 1 (Northernmost).
- Assembling Bent 3.
-Bents 1&2
in place.
-Bent 3
added.
-All 4 bents
(very large picture).
-Facing
South.
+
-Side Views
-Need
a good contractor?
-Nice detail.
-Icing
on the cake.
-Steve Amstutz and
the team from Amstutz Woodworking.
July 25-August 6, The Roof
+
-The ridgepole
is placed.
+
-Another day's progress.
-
+
+
-The view East from the ridgepole
August 5-15, Leaching Field
+
+
August 15, The Porch

August 27, Shingling Begins
-The shingles
were staged for easy deployment.
-Six
inches of copper flashing was added at the drip edge. Then Bituthene®
was applied to the roof to within one inch of the drip edge.
-Four courses
of EcoStartm rubber slate
shingles have been installed. The first course was upside-down (on
purpose).
-Looking
up from under the eves.
August 28, Shingling Continues
-Several more courses have been aded.
-Up close
look
August 30, Shingling Continues
-Nearly done
on the west side.
-Several
braces have been removed.
September 3-4, The Porch
Roof
-Sheets
of copper are laid on the porch roof.
-finished result.
September 10, Solar
-We built the frame and attached the solar panels.
-Kind of biospherical, huh?
September 10, All in review
of course
-Here's the
East side from the Northeast.
-Here's
the East side from the Southeast.
September 30, Santa-proofing
-The Chimney and ridgecaps are installed.

October 8, Roughing
-Electric wires have been roughed in and insulation
has been blown into the ceiling.
-This will
supply the washing machine.
October 9, It's Alive!
-This light
is powered by the solar panels!
October 18, Macrohard Windows®
-South
-East
October 21, Plaster
-BlueBoard
has been installed on all walls and the ceiling.
+
-Then it gets plastered.
-Foliage
October 23, Nature
-Nature says, "Get moving!"
November 4, Interior Progress



November 11, Veterans Day
-From
the South East
-From the South
-Looking
South
-The
Power Plant
-The west side
-The Kitchen
-One of the boys' bed nooks.
-Most children are told to make their
beds. These children were told to make their window.
November 13, When will it
end?
-Trim has been applied.
-Somewhere there are some delighted sailors.
November 18, The View

-From
the stairs, looking at North Pack Monadnock.

-Through a first floor window at sunset.

-The view from the dining alcove.
November 19,
The Leonids
The five of us got up at 4:45 and drove to the house to watch the Leonids. It was 24° and the sky
was partly hazy. There was a halo around the setting full moon. There
were enough gaps in the haze for us to witness about 50 meteorites. A
few times we saw five in a fifteen second span. We also saw the ISS fly over.
November 22,
Moving Day
We rented a U-Haul and moved the piano and
other large items.
November 25,
More Moving Day
Using the pick-up truck, we moved the remaining large items and most everything
else.
-Then we warmed up by the fire.
-Talked
about "Beamed up!"